Amid Eskom Struggles & Load Shedding, South African Switches On Renewables Action Plan

Highlights :

  • South Africa plans to procure 14.771 GW new wind, solar and battery storage capacity under a new action plan to rid the nation of crippling energy shortages.
  • There is a new thrust on moving way from thermal and nuclear to renewable energy, especially solar and wind.

South Africa, long plagued by inefficiencies at national discom Eskon, has decided to move decisively to change the narrative. The country, facing further 2 years of load shedding as projected by Eskom, has made a plan to add 14.771 GW of new wind, solar and battery storage capacity to the national grid. Ever since 2010, the country has been facing ever increasing power shortages leading to hours long load shedding that have become a part of daily life in the country now. The key reason has been the failure of Eskom to switch quickly to renewables, hobbled as it is by its high operating costs and unsustainable debt. The utility, which trades with at least seven countries in the neighbourhood, was pushed to the brink as it supplied power to more people post-apartheid, without a fix on governance quality.

To ensure the new plans actually happen, the country has also dropped an impractical rule insisting on 100% local content in solar panels, reducing it to a much more manageable 30%. The 100% rule was effectively acting as a non-tariff barrier to faster adoption of solar in the country. Currently, the pipeline of private-sector embedded generation projects has grown to over 100 projects representing a total capacity exceeding 9 GW. If these happen, they should help being down load shedding during daylight hours.

The suggestions from the National Energy Crisis Committee (NECOM) are part of its 6-month progress update  on the implementation of the Energy Action Plan, for January 2023. Among other plans, at residential level, a net metering plan is also being finalised to support residential rooftop solar.

South Africa roadmap

South Africa renewable roadmap

Departments have also been instructed to streamline regulatory processes for energy projects. Measures include reducing environmental authorization timeline by half from over 100 days earlier to now 57 days. Grid connection approvals will also be provided within 6 months and the time for registration process has been lowered to 3 weeks, from 4 months till now.

A total of 2.8 GW new renewable energy capacity, thanks to project agreements for 19 projects under Renewable Energy Independent Power Producer Procurement Programme (REIPPPP)—bid window 5 (1.8 GW solar and wind) and 6 from bid window 6 (1 GW)— are expected to soon enter construction.

In the short term, the government hopes to buy around 1 GW power generation capacity from its neighbors after having already imported 300 MW through the Southern African Power Pool (SAPP).

Eskom plans to construct its maiden solar and battery storage projects at Komati, Majuba, Lethabo and other power stations as solar, wind, gas and storage projects at Komati, Sere and Lethabo come online in 2023.

South Africa really needs to get a move on, as one of the most developed countries in Africa. Held captive to vested interests, the extended paralysis in decision making at Eskom has cost the country dear in terms of productivity and competitiveness.