NTPC Gets Tariffs Approved for 3 GW Solar Projects From 2015-16

CERC has approved the tariff obtained by NTPC for 3 GW of solar projects for which it had issued the RfS documents during 2015-16.

The Central Electricity Regulatory Commission (CERC) has approved the tariff obtained by NTPC ltd for 3000 MW (3 GW) of solar projects for which it had issued the Request for Selection (RfS) documents during 2015-16. The projects which were tendered during 2015-16 and successfully awarded latest by 2017 under Batch-II of the State Specific Bundling Scheme under National Solar Mission of the Ministry of New and Renewable Energy (MNRE), have already been commissioned. 

The projects have been set up in Andhra Pradesh, Karnataka, Rajasthan, Telangana, and Uttar Pradesh, and NTPC as the intermediary procurer has already executed (and is honouring) both Power Purchase Agreements (PPAs) for procurement of power with the Solar Power Developers (SPDs) and Power Sale Agreements (PSAs) with Distribution Licenses (Discoms) for sale of power, all before getting the tariffs approved the CERC as per provisions of the Electricity Act.

NTPC Ltd, only in May 2020, had filed a petition with CERC for the approval of tariffs it obtained for the projects. 

 

NTPC 3 GW Solar Tariffs

                     Projects and Successful Bidders

Background:

The first phase of the National Solar Mission launched in 2010 provided for a mechanism of ‘bundling’ of then relatively expensive solar power with thermal power (from the unallocated quota of the Government of India as regards power generated at NTPC coal-based generating station), which was relatively cheaper, in the ratio of 2:1 basis (2 MW of solar power with 1 MW of thermal power) for onward sale of the bundled power to the Distribution Licensees at an affordable price. 

Accordingly, in terms of the Guidelines dated 10.3.2015, issued to provide necessary policy and operational framework for the development of projects under the ‘State Specific Bundling Scheme’, NTPC in its capacity of intermediary agency, issued Request for Selection (RfS) along with draft Power Purchase Agreement (PPA) and Power Sale Agreement (PSA) documents for setting up of grid-connected solar PV power projects in the States of Andhra Pradesh, Karnataka, Rajasthan, Telangana and Uttar Pradesh for an aggregate capacity of 3000 MW and procurement of solar power from the projects being set-up in relation thereto on various dates from 29.4.2015 to 27.10.2016. 

NTPC Submissions:

  • NTPC in support of its petition has submitted that after following a single-stage two envelope bid process followed by an e-Reverse auction in respect of the aforesaid RfS, the successful bidders were selected and the final tariff was arrived at between Rs.3.15/kWh to Rs.5.19/kWh. And that it has agreed to sell the cumulative of 3000 MW of solar power through various projects to the Discoms at the rate between Rs 3.15/kWh to Rs 5.19/kWh plus a trading margin of Rs. 0.07/kWh.
  • It has stated that the solar power projects with a cumulative capacity of 3000 MW have already achieved their respective commissioning and are helping the Discoms to meet their Renewable Purchase Obligations (RPO) requirements in addition to providing power at economical rates. 
  • According to NTPC, the price discovered for procurement of power from the solar power developers under the competitive bidding process was highly competitive at the relevant time and was beneficial to the Discoms and their consumers.

Commission Analysis:

  1. The commission noted that after NTPC concluded the bid process during 2015-16, why did it wait until May 26, 2020, to file the petition for adoption of the tariff. Something that should’ve been done instantly.
      • In its response, NTPC stated that it admits that there has been a delay in approaching the Commission as there was certain ambiguity/ confusion with respect to the jurisdiction of this Commission vis-à-vis State Electricity Regulatory Commissions (SERCs) over the adoption of tariff/ approval of procurement process. 

The commission observed that during the entire period, the Petitioner was fully aware of the fact that there was a need for the adoption of tariffs by an Appropriate Commission and that no such adoption has been done by any Commission. 

“In our view, the Petitioner has displayed utter negligence and lack of diligence by procuring the power and making the related financial transactions over the years in spite of being fully aware of the fact that the tariff of such power has not been adopted as required under Section 63 of the Electricity Act.”

2. After examining all the submissions made by NTPC, to examine whether the process as per the Guidelines by MNRE for bundling had been followed for arriving at the lowest tariff and for selection of the successful bidders, the commission found that the selection of the successful bidders has been made and the tariff of the projects has been discovered by NTPC through a transparent process of competitive bidding in accordance with Guidelines issued by MNRE.

    • NTPC has also certified that the Bid Evaluation Committee had carried out the bidding process as well as techno-commercial and financial bid evaluation in conformity with the provisions of the RfS.

“Thus, in light of the above, the commission adopts the individual tariff for the power projects as discovered through the competitive bidding process with effect from 26.05.2020, the date on which the instant Petition for the adoption of the tariff was filed. Thus, this tariff shall remain valid with effect from 26.05.2020 till the PPAs signed with the successful bidders remain valid.”

For more information click here.

"Want to be featured here or have news to share? Write to info[at]saurenergy.com

Ayush Verma

Ayush is a staff writer at saurenergy.com and writes on renewable energy with a special focus on solar and wind. Prior to this, as an engineering graduate trying to find his niche in the energy journalism segment, he worked as a correspondent for iamrenew.com.

      SUBSCRIBE NEWS LETTER
Scroll