ScOD

Vivid Solaire’s Plea to Align LTA with Revised SCOD of Project Shot Down by CERC

The Central Electricity Regulatory Commission (CERC) has rejected the petition of Vivid Solaire Energy Private Limited to reconsider Long-Term Access (LTA) to coincide with the revised SCOD of project and waive the transmission charges. In its petition, the Pune-based firm had filed a petition seeking a waiver for the levy of transmission charges by CTUIL […]

Read more

CERC Rejects ReNew Power Plea On Force Majeure for 250 MW Wind Project

In an order dated July 29, the Central Electricity Regulatory Commission (CERC) has rejected multiple contentions by ReNew Power regarding a 250 MW ISTS connected wind energy project for 250 MW that it had won in 2018. ReNew had made SECI, as well as multiple state discoms that are buying power from the project respondents […]

Read more
      SUBSCRIBE NEWS LETTER
Scroll